QF Solver 0.2.5a0 objective-mode execution plan

Objective for the future execution process

Implement and qualify the 0.2.5a0 bounded unified nonlinear structural mechanics scope in strict gate order, preserving the complete 0.2.4 baseline and producing reproducible evidence for each work package before starting dependent work.

Mandatory operating loop

AUDIT -> IMPLEMENT ONE WP -> VERIFY -> BENCHMARK -> CORRELATE -> GATE
      -> GO to a dependent WP, or STOP/document if the gate remains OPEN

The execution process must never convert missing evidence, unavailable software or elapsed time into a PASS.

Exact execution order

  1. WP0: freeze v0.2.4a0 baseline and close 025-G00.
  2. WP1: close every inherited 0.2.4 V&V debt and 025-G01.
  3. WP2: unify and verify TET4/HEX8 geometric nonlinear core; close 025-G02.
  4. WP3: verify sparse linear buckling; close 025-G03.
  5. WP4: verify one sparse arc-length method; close 025-G04.
  6. WP5: unify frictionless finite-sliding contact; close 025-G05.
  7. WP6: verify mandatory pairwise couplings; close 025-G06.
  8. Ask Owner whether WP7 friction is promoted; otherwise record NOT_IN_SCOPE.
  9. WP8: characterize performance on every completed mandatory capability.
  10. WP9: execute adversarial/failure matrix.
  11. WP10: complete bounded external-correlation matrix.
  12. WP11: run full regression, docs, packaging and smoke installation.
  13. WP12: regenerate final-SHA evidence and request Owner release decision.

WP3 and WP4 may run in parallel after G02. Profiling and adversarial tests may be prepared earlier, but their gates cannot close before the corresponding function gate.

Per-WP execution checklist

  1. Read authoritative requirements, formulas, risks and gate rows.
  2. Record baseline tests and numerical outputs before editing.
  3. Make the smallest architecture-compatible change.
  4. Run focused unit and element tests.
  5. Run global benchmark and sensitivity study.
  6. Run external correlation when the gate requires it.
  7. Update evidence, limitation and traceability records.
  8. Close the gate only when every acceptance item has an artifact.
  9. Run prerequisite non-regression before moving on.

STOP rules

Stop the dependent branch and leave the gate OPEN when any of these occurs:

  • stress/strain measures are not approved for a coupled formulation;
  • tangent FD or objectivity fails;
  • a failed step corrupts committed state;
  • sparse paths require an unbounded dense allocation;
  • mesh/load-step studies do not converge without a documented explanation;
  • external formulations are not comparable;
  • a mandatory 0.2.4 regression appears;
  • evidence cannot be tied to the exact tested SHA.

Independent work may continue only when its dependency path does not include the open gate.

GO rules

GO requires the gate row to contain: exact SHA, environment, commands, results, artifacts, limits, reviewer and explicit status. A green test process alone is not a closed gate.

Release boundary

The future execution process may prepare commits and release artifacts when instructed, but must not tag, create a GitHub Release or publish to PyPI without a separate Owner instruction after 025-G12.